Bidwells was retained to advise and manage the construction of two new, high quality, 4-bed detached dwellings in a popular necklace village, close to Cambridge.
What we did
-
Oversaw the demolition and site clearance of a previously dilapidated detached bungalow
-
Managed the process through building control, procurement and onto site, incorporating works monitoring, contract administration and CDM H&S services
-
Advised on the specification and level of internal finishes to ensure the properties were fit for the Cambridge market
-
Managed the competitive single stage tendering process, ensuring that the design was incorporated into a specification of works
-
Undertook full Contract Administration of the project, liaising with the client’s internal consultants, chairing progress meetings and managing change control procedures to incorporate requested design changes without delays as works progressed on-site
Result
-
The client was provided with a high quality development within a sought after village location within Cambridgeshire and achieved higher sale values than anticipated
30
week build programme